Overview
Sharps Workplace Services was entrusted by David Morris London, a world-renowned fine jeweller, to support a high-profile exhibition at the historic Tower of London. With only a one-hour setup window between public closing and guest arrival, our team executed a precise and time-critical operation. The relocation included delivery, setup, and retrieval of delicate exhibition equipment, with added logistical complexities due to the heritage venue.
Project Scope
- Event Location: Tower of London
- Setup Window: One hour between public closure and guest arrival
Services Delivered:
- Project consultancy and logistics planning
- Equipment retrieval from Sharps storage and the client’s HQ
- Timed delivery and installation at venue
- Dismantling and post-event retrieval
- Secure storage and returns
- Facilities management support
Pre-Move Planning
A strategic planning meeting was held between our Prince2-certified Project Manager and the client’s event planning team. All logistical elements were reviewed, including:
- Specific items required from Sharps’ storage
- Equipment collection from the client’s central London HQ
- Venue access limitations and time constraints
- Post-event dismantling and return procedures
The entire team received a detailed briefing to ensure awareness of timelines, site access conditions, and item handling protocols.
Execution & On-Site Logistics
- All equipment was retrieved and loaded from storage, and collected from HQ during the working day
- The team arrived at the Tower of London ahead of schedule to maximise setup time
- Despite the constraints of the heritage venue, all items were carried up multiple flights of stairs and installed within the critical one-hour window
- The team remained on-site late into the evening to dismantle and retrieve equipment following the event
- Items were returned securely to the Sharps storage facility and client HQ the following day
Results
- Exhibition installed and removed flawlessly within critical time constraints
- Zero disruption to event operations or guest experience
- All logistics completed with care for venue guidelines and display item sensitivity
- Continued partnership with the client following successful project delivery
Client Feedback
“Sharps Workplace Services played a key role in the smooth execution of our Tower of London exhibition. Their professionalism and strict adherence to our timeline ensured everything was in place exactly when needed. We appreciate their continued support for our storage and facility needs.”
— Events Lead, David Morris London